Current Extension Projects

Finally! The Adair Road Water Line Extension has been approved by the Public Service Commission of West Virginia. This extension will allow us to provide water further down Adair Road and to Little Rich Creek Valley Road, Daugherty Road, John Deere Drive, Peach Tree Lane, Greasy Ridge Road, Carter Lane, and Pinhook Road. If you are interested in having a water tap installed during project construction, please contact the office as soon as possible.

The bidding process concluded on May 28, 2025 and we are awaiting the final bid evaluation from our engineers and the USDA. This should be completed by the first part of June 2025.

Here are the tasks to be completed as well as targeted completion dates:

Pre-Bid Showing: April 30, 2025

Open Bids: May 22, 2025 May 28, 2025

Engineer provides bid evaluation to Red Sulphur PSD & USDA: May 30, 2025

Red Sulphur Issues Award of Notice: June 17, 2025

Red Sulphur Awards Construction Contract to Lowest Responsible Bidder/
Preconstruction Conference: August 7, 2025

Substantial Completion: February 3, 2026

Final Completion: March 5, 2026

Red Sulphur PSD is currently working with engineers and the West Virginia Regional Planning Commission to extend sewer service down WV Route 12 to areas in Cashmere and Ballard. If approved to move forward and the funding is available, this would impact approximately 125 households and businesses.